Completed Projects

Completed Projects 2012-2017

Project Description

Project Phase

New Academic Building

Completed

Renovations at H, I and K Wings at Campus Center

Completed

Renovate Clark Center Drop off Area and Fields Entry

Completed

Replace Fuel Tanks at Service Group

Completed

Replace Elevators Campus Wide

Completed

Repair Natural Sciences and Clark Emergency Elec. Generator

Completed

Athletic Fields Rehab

Completed

Replace Campus Center Facades

Completed

Heat Plant Co-Generator Improvements

Completed

Replace Library Roof at Campus Center

Completed

Repairs to Various Buildings Due to Hurricane Damages

Completed

Demolish Academic Buildings B & C

Completed

Replace HVAC Controls at Student Union

Completed

Build 3D Modeling Lab at F Wing Campus Center

Completed

Replace Road Salt Sand Shed

Completed

Parking and Traffic Study

Completed

Removal of Fuel Oil Tank

Completed

Add Redundant AC at Data Center

Completed

Bridges - Snow Guards

Completed

Replace Air Handler Units at Campus Center H Wing

Completed

Carbon Monoxide Detection

Completed

ADA Door Openers

Completed

Acoustic Panel Repair at Heat Plant

Completed

Parking Lot Walkway Replacements

Completed

Replace Service Group Garage Doors

Completed

Loading Docks Rails

Completed

Rehab Natural Sciences Building Cooling Tower

Completed

Study - Campus Center – F - Wing Renovation

Completed

Phase and Surge Study- NSB Renovation / STEM Addition

Completed